you are required to compute the mcvs and lcvs and also to reconcile the standard and 621615
The following details relating to the Product A during the month of March 2002 are available. You are required to compute the MCVs and LCVs and also to reconcile the standard and the actual cost with the help of such variances.
Standard Cost per unit: |
|
Materials |
50 kg @ Rs. 40 per kg |
Labour |
400 hrs @ Re. 1 per hr |
Actual Cost for the month: |
|
Materials |
4,900 kg @ Rs. 42 per kg |
Labour |
39,600 hrs @ Rs. 1.10 per hr |
Actual production for the month is 100 units.