what is the standard quantity of material and the standard labor time for july 642446

(DM & DL variances) Schmidt Co. has the following standard material and labor quantities and costs for one unit of Product SWK#468:

Material

1.85 pounds @ $3.50 per pound

Labor

0.04 hours @ $12 per hour

During July, the purchasing agent found a “good deal” on the raw material needed for Product SWK#468 and bought 100,000 pounds of material at $3.15 per pound. In July, the company produced 48,000 units of Product SWK#468 with the following material and labor usage:

Material

95,000 pounds

Labor

2,200 hours @ $12.10 (due to a renegotiated labor contract)

a. What is the standard quantity of material and the standard labor time for July?

b. Calculate the material and labor variances for July.

c. Did the purchasing agent make a “good deal” on the raw material? Explain.